|  | CONSTRUCTION
AND
MAINTENANCE UPDATE
Western Gas
Resources, Inc. is the physical operator and construction manager
of the Fort Union gathering system.
- Began purging the system on August 18th
- Began line packing the system on August 20th
- First day of flow on September 1, 1999
- Expansion in service date of September 1, 2001
- Moving 450,000 MMBtu per day as of April 1,
2003
|
|